Feldmoching - Freising, Bavaria
Time frame: 07/2018 - 05/2019
Location: Neufahrn b. Freising, Rosenheim, Bavaria
Scope:
- Delivery of approximately 11,100 tonnes subgrade protection layer particle size 1 and 5,300 tonnes particle size 2 according to Deutsche Bahn Standard 918062
- Rental, preparation, maintenance and dismantling of storage areas of 10,000 m2, 11,000 m2 and 15,000 m2
- Provision of construction machinery such as high-speed dozers, tracked excavators, wheel loaders, etc.
- Use of low loaders, 3- and 4-axle trailers and semi-trailers
- Construction and dismantling of 2,500 m2 of construction roads and a 0.60 m superstructure to protect archaeological sites
- Building, dismantling and disposing of asphalt driveway
- Transport of 1,800 tonnes of trackbed protection layer particle size 1 from Rosenheim to Neufahrn
- Loading of silo wagons with trackbed protection layer and ballast, as well as unloading and stockpiling of old material from silo wagons