Bulgaria
Time frame: 2012 - 2015
Location: Septemvri, Bulgaria
Scope:
- Extension and modernization of the Septemvri – Plovdiv line as part of the high-speed railway line between the two largest cities, Sofia and Plovdiv
- Independent operation of a quarry in the immediate vicinity of the railway line
- Foundation of the subsidiary VE-Log Bulgaria EOOD
- Production and supply of certified track ballast and particle mixtures
- 90,000 tonnes new gravel
- 50,000 tonnes trackbed protection layer particle size 1
- 170,000 tonnes trackbed protection layer particle size 2
- 65,000 tonnes soil exchange material 0/63