Neukirchen - Vilseck, Germany
Time frame: 04/2019 - 09/2019
Location: Vilseck, near Sulzbach - Rosenberg, Bavaria
Scope:
- Embankment rehabilitation, 2,100 m in length
- Embankment removal and preparation of work area for Bauer company, Schrobenhasen
- Layer-by-layer construction after completion of the mixed-in-place columns by Bauer, including laying of geogrids (longitudinal and lateral) as well as trackbed protection layer and new ballast subgrade
- Installation of 40,000 tonnes of frost protection layer and 21,000 tonnes of subgrade protection layer particle size 1 produced and delivered by VE-Log
- Rental, establishment, maintenance and dismantling of 75,000 m2 of storage area, of which 11,800 m2 paved
- Machinery: 5 crawler excavators, 4 wheel loaders, 1 mobile excavator, 1 bulldozer, 2 high-speed dozers, 2 bulldozers, 12 tractors with dump trailers, various lorries, rollers and ancillary equipment
- Disposal of 13,700m3 of drilling spoils